Controls & Transformers

Questions and Answers

MFDC stands for MID FREQUENCY DIRECT CURRENT. There are two components needed to convert standard alternating current (AC) to MFDC. They are the weld control and the transformer. The weld control is made up of two major areas, the first being the Bridge Rectifier where the three phase 60 Hz AC input is rectified into a DC output. The second section is the inverter, or H=Bridge, which is a polarity reversing switch. This switch also operates at the desired increased frequency of 1000 Hz. In the H-Bridge the rectified DC input is converted back into a single phase AC square wave output at 1000 Hz frequency, as shown below.
This mid frequency AC is the input to the primary of the transformer. The diodes in the transformer then converts this AC back to DC (MFDC) for welding in the secondary circuit.

In many facilities it is beneficial to insure that the multiple welders in a station not fire at the same time to prevent a sudden large draw on the plant power supply. To spread this out cascade controls can be employed where one control will sequence through several contactors in sequence. The sequence and separation between the welds can be controlled to give an appropriate modest draw on the power supply.

In North America the power grid is 60 hertz. All schedules and operations are based upon that power.  In other parts of the world power is generated at other power levels. Many use 50 hertz. If one has a good weld schedule in a 60 hertz area and a new operation were set up in a 50 hertz region a conversion would be needed for weld time. The formula is:

Weld Time @60 Hz X (50/60) = Weld Time @ 50 Hz

                            OR

Weld Time @50 Hz X (60/50) = Weld Time @60 Hz

Pressure, current and time (PCT) are the basic functions performed by the resistance welder. These functions are controlled or initiated by the weld controller. It initiates each step when told to start the weld process by input from the foot switch or automation PLC. The controller allows time for each step to operate and controls the current amplitude. In simplified form this is Squeeze, Weld and Hold. The squeeze sequence allows the pressure system to build up the force to contain the weld. The weld function is the actual current flow and is totally controlled by the weld controller. It regulates the amplitude and time of current flow. Hold is the period which allows the weld nugget to cool down and solidify under force. The controller regulates this time.

 

Most published weld schedules are published in terms of AC welding. If you acquire a new control and it is an inverter/mid frequency control you probably will program in milliseconds rather than the traditional AC Cycles. The mathematical conversion is:


1 AC CYCLE = 16.7 MILLISECONDS

Have a Question?

Do you have a question that is not covered in our knowledgebase? Do you have questions regarding the above article? Click here to ask the professor.